Quantcast
Channel: Greenwich Free Press
Viewing all articles
Browse latest Browse all 1788

Greenwich Drivers Told to Anticipate Brookridge Drive Road Closure

$
0
0
IMG_1604

IMG_1604Starting on July 11, a small bridge located on Brookridge Drive will be closed for approximately four months.

The project, officially called the Brookridge Drive Bridge Superstructure Replacement project, is scheduled to be completed by December of this year.

The road will be closed at the bridge site from July 11 to an unknown day in November.

Alfred Benesch & Company (based in Glastonbury, CT) was given a contract of $256,306.00 to complete this project.

The following detour will be established:

Traffic wanting to travel southbound on Brookridge Drive shall utilize Fairfield Road to Stanwich Road to Route 1.

Traffic wanting to travel northbound on Brookridge Drive shall utilize Route 1 to Stanwich Road to Fairfield Road.

IMG_1605

The bridge on Brookridge Drive. Credit: Kai Sherwin.

 

The bridge on Brookridge Drive. Credit: Kai Sherwin.


Image

Email news tips to Greenwich Free Press editor Leslie.Yager@GreenwichFreePress.com
Like us on Facebook

Twitter 


Viewing all articles
Browse latest Browse all 1788

Trending Articles